Through implementing this plan, we not only ensure the quality of highway, but also improve the schedule of construction.
通过实施该方案,既保证公路质量,又提高施工的进度。
The Augustine panel questioned the cost, design and construction schedule of the rocket in a report submitted to the White House for consideration.
奥古斯汀专项研究小组质疑提交给白宫考虑的报告中的成本、设计以及建设计划。
Figure 10: Sample master schedule that has the overall Construction phase divided into three six-week periods, with important delivery dates at the end of each iteration.
图10:用每个迭代最后的重要的交付日期对整个构建阶段分成三个六周周期的综合时间表进行采样。
He said the 10-month construction freeze will end on schedule on September 26th, according to a previous decision of the Israeli Cabinet.
他说,根据以色列内阁先前的决定,冻结定居点建设10个月的决定将按计划在9月26日结束。
Supervise, co-ordinate and schedule the activities of workers who operate cranes and construction, paving, drilling, railway maintenance and other similar heavy equipment.
监督,协调和统筹安排操作起重机和施工,摊铺,钻井,铁路维护及其他类似的重型设备工人的活动。
Understands from city live built bureau, on the premise of ensure the construction quality and safety, are accelerating the construction schedule of each link quality.
从市住建局了解到,在确保施工质量和安全的前提下,施工方正在加速每个环节的工程进度。
Other work must be centered on the construction schedule to adapt to the requirements of the arrangements.
施工中的其他工作必须围绕着并适应施工进度计划的要求安排。
In this paper author introduces the application of this article in road bidding, construction management, engineering schedule, engineering quality, engineering cost and contract management.
着重论述了本条款在公路投标、施工组织、工程进度、工程质量、工程费用、合同管理各个阶段中的应用。
We should work according to the overall schedule chart (the construction time schedule) of the project.
我们应该根据工程项目标总进度表(构筑进度表)工作。
Construction diversion is important component of comprehensive design in water conservancy projects and has direct relationship with the whole engineering schedule and cost.
施工导流是水利枢纽工程总体设计的重要组成部分,直接关系到工程总进度和工程总造价。
In the construction of highway, the construction organization of through cut and the construction quality will influence the construction schedule and slope stability.
在公路建设中,路堑开挖施工组织是否合理、施工质量如何,将影响施工进度和边坡的稳定。
In the practical application of power transmission lines to solve the river sealed route, schedule, safety, environmental damage relationships, reducing construction costs.
在输电线路工程实际运用中解决了河流封航、进度、安全、环境破坏的关系,降低了施工费用。
Composition, installation procedure and features, construction schedule and quality control and inspection of sulphur-burning sulphuric acid plants are reviewed.
介绍了硫磺制酸装置的组成、安装工艺及特点、施工进度计划和质量控制检查。
Strengthen construction management and extend use new management method can promote engineering schedule and shorten time of project and saving fund and reduce cost.
只有加强施工管理,推广使用新管理方法,才能促进工程进度,缩短工期,节约资金,降低造价。
Standard brick upon the occurrence of these problems, construction will be disrupted, serious impact on the building construction schedule and project quality.
标砖一旦发生这些问题,施工将被打乱,严重影响建筑物的施工进度和工程质量。
Standard brick upon the occurrence of these problems, construction will be disrupted, serious impact on the building construction schedule and project quality.
标砖一朝发生这些个疑难题目,施工将被打乱,严重影响修建物的施工进度和工程质量。
Handle a whole team of engineering and the whole design and construction process; ensure new project complies with requirements of quality products, safety, cost and schedule.
管理整个工程团队、相关设计与施工过程控制;确保项目按质量、安全、费用与进度的要求完成。
Construction of the project implementation, to develop specific programs and project implementation process on the installation schedule and make adjustments to control.
项目实施时制定具体施工方案和项目执行过程中对安装进度计划并进行调整、控制。
With practical projects, authors introduce the construction method and principle, schedule, plan and technical points of the lifting construction of steel pipe arch truss segments.
通过工程实例,介绍了钢管拱桁架节段吊装施工的方法与原理、施工程序、施工布置及技术要点等。
This paper probes into the countermeasures for doing well the construction management from aspects of the schedule control, cost control, and quality control, etc.
从工程的进度控制、成本控制、质量控制方面探讨了搞好施工管理的对策。
In the control of construction schedule for hydropower projects, risk analysis of the schedule is a key.
工程施工进度风险分析计算是施工进度控制中的重要环节。
The project completion probability is discussed, which fully describes the uncertainty of construction sequence schedule and provides basis for analysis of time limit.
进行了完工概率分析,较好地描述了施工进度计划的不确定性,为施工工期论证分析提供了依据。
Construction of the project implementation, to develop specific programs and projects in the implementation process on the installation schedule and make adjustments to control.
项目实施时制定具体施工方案和项目执行过程中对安装进度计划并进行调整、控制。
The functions and characters of the software P3 and its application to work out the construction schedule of a pumped storage power station are described.
介绍了P 3软件的功能和特点以及在某抽水蓄能电站工程施工进度计划编制中的应用过程及成果。
During the process from plan to completion, the project team has experienced a series problem center on cost of the building, construction quality, construction schedule and so on.
在项目从设计团队的笔下理想成为落地实物的过程中,经历了围绕项目造价、施工质量、工期进度等一系列问题的艰难博弈。
In roadbed construction, excessive soil is used to fill subgrade because of weather and construction schedule constraints and other reasons.
在公路路基施工中,天气及施工工期的限制等原因,会经常遇到采用过湿土填筑路基的情况。
The principle to constitute the reasonable schedule in quick construction is presented and the application of concurrent construction in water resources and hydropower engineering is researched.
构想了快速施工下合理工期的制定原则方法和并行施工在水利水电工程中应用的一些思路。
Through active promotion of the standard, production and construction requirements on power material procurement are met in quality, quantity and delivery schedule and the procurement cost is lowered.
通过积极推行标准,达到保证电力物资采购在质量、数量、供贷时间上满足生产,建设的要求,并降低了采购成本。
The each time parameter of construction schedule network planning in the graph may be exposed immediately, the total float and the free float of each work especially.
图上可直接展示施工进度网络计划的各时间参数,特别是各工作的总时差和自由时差。
The each time parameter of construction schedule network planning in the graph may be exposed immediately, the total float and the free float of each work especially.
图上可直接展示施工进度网络计划的各时间参数,特别是各工作的总时差和自由时差。
应用推荐