计日工俗称“点工”,在施工过程中,完成发包人提出的工程合同范围以外的零星项目或工作,按合同中约定的综合单价计价。
n. journeyman
misc. dataller
... data-linkage 数据衔接 dataller 计日工 datascope computer output microfilm 数据显示器计算机输出缩微胶卷 ...
基于16个网页-相关网页
对于不可预见的项目;工程量清单中用计日工(Day Works),专项暂定金(Specific Provisional Sum)和总暂定金(Provisional Siun)列出。
基于16个网页-相关网页
计日工作单价 daywork rate
计日工资 daily wage ; day rate payment ; [劳经] daily wages
按计日工的方式 on the daywork basis
计日工表 Daywork Schedule
计划完工日期 intended completion date ; [基经] scheduled completion date
计日工资率 day work rate
估计完工日期 estimated date of completion ; estimated completion date ; EDC
按日计工资 datable
预计完工日期 estimated date of completion ; estimated complete date
如果合同中没有计日工报表,则本款不适用。
If a Daywork Schedule is not included in the Contract, this Sub-Clause shall not apply.
如果合同中未包括计日工作计划表,则本款不适用。
If a daywork schedule is not included in the Contract, this Sub-Clause shall not apply.
对于一些小的或附带性的工作,雇主可指示按计日工作实施变更。
For work of a minor or incidental nature, the employer may instruct that a Variation shall be executed on a daywork basis.