Roller compacted concrete (RCC) will be used in section no. 6-no. 15 of the spillway dam, section no. 5 of the non - overflow dam near the left side bank and the left guide wall of Wan 'an Project.
万安水电站二期主体工程溢流坝6 ~ 15坝段、左岸非溢流坝5坝段和左导墙部分拟采用碾压混凝土筑坝技术。
The second stage is to close the left bank main river bed, divert the stream to the right bank open channel and build the spillway section in the mian river bed and the powerhouse on the left bank.
二期工程围左岸主河床 ,右岸明渠 (建于一期 )导流 ,建主河床泄洪坝段及左岸电站厂房。