网络释义

  master programme

红皮书涉及到计划的条款有第8条,其中8.3条规定了在收到开工通知28天之内,承包商应向业主提交总进度计划master programme),如果业主在收到总进度计划21天未提出不符合合同要求的通知,则合同双方就按照本计划进行工作的安排。

基于32个网页-相关网页

短语

项目总进度计划 project master schedule

施工总进度计划 master construction schedule plan

总生产进度计划 Master Production Schedule ; MPS

总体综合进度计划 overall integrating schedule

总生产进度计划 Master Production Schedule

 更多收起网络短语

双语例句

  • 按照批准工程进度计划协调专业进度计划实际运转督促进度计划实施

    According to approval project general schedule, coordinating the practical operating of every specialty plan, and supervising the carrying out of process plan.

    youdao

  • 施工进度计划只是一个计划存在风险

    The construction schedule is only a plan, which always has risk.

    youdao

  • 买方技术人员到达工作现场双方工地代表应对进度月度工作计划进行协商达成一致。

    A general working schedule and a monthly plan shall be negotiated and agreed upon by the Site Representatives of both Parties after the arrival of the Seller's technical personnel at the Job Site.

    youdao