例如,顾客或实施组织签发的事先确定的预算或任何强加的日期(进度里程碑)。
For example, a predefined budget or any imposed dates (schedule milestones) that are issued by the customer or performing organization are included.
然而,可举例说明,关键路线可以止于处于项目进度表中间,并受到“不迟于完成”类型的强加日期进度约束的某一计划里程碑。
However, a critical path can end, as an example, on a schedule milestone that is in the middle of the project schedule and that has a finish-no-later-than imposed date schedule constraint.