流水步距是流水作业时两个施工过程先后进入施工的时间间隔。流水步距的数目取决于参加流水作业的施工过程数,如施工过程为n个,流水步距数则为n-1。确定流水步距时,应始终保持施工过程的工艺顺序; 保持各施工过程的连续作业;使前后两施工过程施工时间搭接最长。
...流水节拍;流水步距;网络计划 [gap=707]Key words: flow construction; frequency of continuous construction; flowline pace; network plan ...
基于6个网页-相关网页
揭示了段时差、假定段步距和流水步距之间的内在联系;
The internal relations between section slack, supposing section pace and flowing pace hane been brought to light.
认为流水步距的定义应为相邻的两个施工班组相继投入施工的间隔时间,不包括组织间歇、技术间歇、搭接时间等时间间歇。
The flowline pace should be defined as the interval time which the neighbouring workgroup has spent in succession, excluding organizing interval, technical interval, joining interval, etc.