A Type II condition allows the contractor additional cost recovery if the actual conditions differ from what could have been reasonably expected for the work contemplated in the contract.
在类型II条件中,如果实际条件与对合同中工程合理期望的条件存在实质性的差别,类型II条件给予承包商额外的成本回收。
A Type II condition allows the contractor additional cost recovery if the actual conditions differ from what could have been reasonably expected for the work contemplated in the contract.
在类型II条件中,如果实际条件与对合同中工程合理期望的条件存在实质性的差别,类型II条件给予承包商额外的成本回收。