• Would there be any which are discernible to emerge during project duration?

    项目期间出现任何可以发现的困难和问题吗?

    youdao

  • However, an increase in the size of the plumbing crew reduced the project duration to 229 days.

    不过增加大小管道船员减少项目执行期已229天。

    youdao

  • Cost itself may be a product of other factors, including the project duration, resources, and environment.

    费用本身可能是产品其它要素包括产品工期资源环境等。

    youdao

  • Abstract: The influencing factors of the source of construction project duration extension are complicated.

    [摘要]建设工程项目工程延期影响因素错综复杂

    youdao

  • This is a very simple and useful method in practice because it is not necessary to asunune a distribution of the project duration.

    方法需要各工作延续时间分布作出假定,因此具有广泛的实用性

    youdao

  • The objective of fast tracking a project is to: Increase productivity. Reduce project duration. Increase schedule tracking controls.

    项目快速跟进目标提高生产效率减少项目历时提高进度跟踪控制降低项目风险。

    youdao

  • The optimal size of resource is, therefore, defined as the minimum size of resource required to keep the project duration a minimum.

    最佳大小资源所以被界定最小尺寸的资源必须保持项目持续时间减少到最低限度。

    youdao

  • The increase in project duration normally translates into an increase in the cost of Labour as the Labour is deployed on daily wages basis.

    增加项目期限通常转化为增加劳工成本,劳工部署工资基础上。

    youdao

  • The ideal pilot project sits at the confluence of project size, project duration, project importance, and the engagement of the business sponsor.

    理想试点项目需要综合项目大小、项目持续时间、项目重要性以及业务发起人参与度

    youdao

  • For complex engineering construction system, resource scheduling of limited project duration-resource leveling is an important and difficult problem.

    对于复杂工程施工系统工期一定、资源均衡资源进度计划需要解决的一个重要且有相当难度的问题。

    youdao

  • In contrast of the two methods' results, this paper attempts to find reasonable plan duration and make reasonable proposals to the original project duration plan.

    对比两种方法计算结果,尝试找到一个合理计划工期工程工期计划提出一定建议

    youdao

  • Project scheduling with heterogeneous efficiency workforce to minimize project duration is considered, and the corresponding integer linear programming is presented.

    研究了员工具有异质效率最小化项目工期的项目调度问题建立了相应整数线性规划模型。

    youdao

  • One difference is that you can assert, for instance, that the plan-driven approach will extend our project duration from twelve to fourteen weeks, an increase of two weeks.

    区别之一就是能够断言例如计划驱动方法把您的项目周期十二扩展四周,增加周的时间。

    youdao

  • The methods of identifying critical chain with the goals of minimum project duration and duration-cost tradeoff are put forward. Finally a scheduling example is given to prove the methods' validity.

    然后,工期最小目标与工期-成本权衡目标建立关键识别方法模型,通过算例验证了方法的有效性

    youdao

  • Of course, for the project to have acceptable risk, this must be done for each of the tasks, leading to almost doubling the duration.

    当然对于拥有可接受风险项目来说,必须每个任务这样做这将导致几乎将持续时间加倍

    youdao

  • Project estimation tools provide estimates of effort and duration based on the available information.

    项目估算工具根据可用信息提供工作持续时间估计

    youdao

  • You'll evaluate the remaining work to see if the project will be completed within the original effort, cost, and duration plans.

    评估那些剩余的工作看看项目是否可以按照初始计划中估算的工时成本以及期限完成

    youdao

  • Many project managers have different "rules of thumb" for the maximum duration of any one task, but a common one is that most tasks should not exceed two weeks.

    对于任一任务最大持续时间许多项目经理都有不同经验一般而言,大多数任务超过周。

    youdao

  • For example, a metric that does not correlate to the project cost or duration cannot aid in assessing the variance reduction in the iterations.

    例如,与项目成本持续时间无关度量标准不能帮助评估迭代中的方差削减

    youdao

  • I. Duration - a short project would help skeptics to say that Agile works for small projects.

    持续时间—项目人怀疑敏捷只项目有用

    youdao

  • What is our current test creation velocity and what has it been for the duration of the project?

    我们当前测试创建速度多少以及在项目过程曾经是多少?

    youdao

  • What is our current test execution velocity and what has it been for the duration of the project?

    我们当前测试执行速度多少以及在项目过程曾经是多少?

    youdao

  • Therefore, any potential higher, up-front costs are more easily recovered over the duration of a project (see Sidebar).

    因此项目过程中,任何可能更高预先的成本容易回收参见工具条)。

    youdao

  • Those in our industry understand how difficult it is to accurately determine up front the exact scope, cost, or duration of a significant project.

    我们知道我们行业准确地制定一个重大项目功能范围价格或者时间非常困难

    youdao

  • Smaller companies are viewed as riskier partners that are vulnerable to the loss of key personnel and "may not have the financial muscle to survive for the duration of a project," the authors said.

    公司容易视作危险合作者,因为他们容易流失核心技术人员,还可能"缺乏足够经济力量在项目的开发周期中生存下来,"这位官员还说。

    youdao

  • The time spent properly planning the project will result in reduced cost and duration and increased quality over the life of the project.

    花些时间进行适当规划可降低成本缩短时间提高项目生命周期内的质量

    youdao

  • Medium project: Has a budget of $100,000-$500,000, a team size of six to twelve, and a duration of six months to a year.

    中等项目预算$100,000-$500,000,团队规模十二人项目进行时间为个月

    youdao

  • After the workplan has been updated, determine whether the project will be completed within the original effort, cost, and duration.

    更新工作计划后,判断项目是否按期保质不超预算完成

    youdao

  • With that in mind a project plan was defined with an estimated duration of six days.

    这样一个项目计划天之内制定出来

    youdao

  • With that in mind a project plan was defined with an estimated duration of six days.

    这样一个项目计划天之内制定出来

    youdao

$firstVoiceSent
- 来自原声例句
小调查
请问您想要如何调整此模块?

感谢您的反馈,我们会尽快进行适当修改!
进来说说原因吧 确定
小调查
请问您想要如何调整此模块?

感谢您的反馈,我们会尽快进行适当修改!
进来说说原因吧 确定