• If a daywork schedule is not included in the Contract, this Sub-Clause shall not apply.

    如果合同包括计日工作计划表,则适用。

    youdao

  • If a Daywork Schedule is not included in the Contract, this Sub-Clause shall not apply.

    如果合同中没有计日工报表,则适用

    youdao

  • Unless and until the Employer receives this guarantee, this Sub-Clause shall not apply.

    除非直到雇主收到保函适用

    youdao

  • "Contract agreement" means the contract agreement (if any) referred to in Sub-Clause 9. 1.

    合同协议第9. 1款所指的合同协议(有的话)。

    youdao

  • These records shall be kept on the Site and shall be used exclusively for the purposes of this Sub-Clause.

    上述竣工记录保存现场仅限用于目的

    youdao

  • Retention Money" means the aggregate of all monies retained by the Employer pursuant to Sub-Clause 60.2(a)."

    保留是指雇主根据第60.2(a)规定留存所有金额总和

    youdao

  • Final statement "means the statement defined in Sub-Clause 14.11 [Application for Final Payment Certificate]."

    最终报表第14.11【最终支付证书的申请】中定义的报表。

    youdao

  • A filter (e.g., SQL statement sub-clause) is used to filter out data records not belonging to the current tenant.

    使用筛选器(例如sql)筛选掉属于当前租户数据记录

    youdao

  • The requirements of this Sub-Clause are in addition to those of any other Sub-Clause which may apply to a claim.

    各项要求适用于索赔任何其他条款的追加要求。

    youdao

  • The covenants clause is composed of sub-clauses such as negative pledge, pari passu, financial covenant and so on.

    约定事项"包括众多条款消极担保、比例平等、财务约定事项

    youdao

  • A Commissioning Certificate has been issued, or is deemed to have been issued, in accordance with this Sub-Clause.

    根据本款规定试运行证书已经签发或者视为签发。

    youdao

  • Final payment certificate "means the payment certificate issued under Sub-Clause 14.13 [issue of Final payment certificate]."

    最终支付证书按照第14.13【最终支付证书颁发】颁发的支付证书。

    youdao

  • One half of the retention shall be paid by the Employer to the Contractor with in 14 days after issuing the notice under Sub-Clause 8.2.

    雇主根据第8.2规定颁发通知14天内向承包商支付一半保留金

    youdao

  • The proposal shall be prepared at the cost of the Contractor and shall include the items listed in Sub-Clause 13.3 [Variation Procedure].

    承包商应自费编制此类建议书其包括在第13.3变更程序】所列条目中。

    youdao

  • Contract price "means the price defined in Sub-Clause 14.1 [the Contract price], and includes adjustments in accordance with the Contract."

    合同价格第14.1【合同价格】定义价格,包括根据合同所做的调整

    youdao

  • Approval by the Project Manager of the Contractor's drawings shall not relieve the Contractor from any responsibility under this Sub-Clause.

    项目经理承包商图纸批准解除款规定的承包商的任何责任

    youdao

  • The Contractor shall, if required by the Engineer so to do, copy to the Employer all accounts sent to the Engineer pursuant to this Sub-Clause.

    工程 师要求这样的话,承包商应将所有根据送交工程师的详细报告复印送交雇主

    youdao

  • However, the total amount due under this Sub-Clause shall not exceed the maximum amount of delay damages (if any) stated in the Particular Conditions.

    计算赔偿总额不得超过专用条件规定误期损害赔偿费最高限额(如果有)。

    youdao

  • If a Contractor's Document so fails to comply, it shall be rectified, resubmitted and reviewed in accordance with this Sub-Clause, at the Contractor's cost.

    如果承包商文件确实如此符合文件由承包商承担费用,按照修正,重新上报,并审核

    youdao

  • In this Clause, "insuring Party" means, for each type of insurance, the Party responsible for effecting and maintaining the insurance specified in the relevant Sub-Clause.

    本条中,“保险含义是指根据相关条款规定投保各种类型保险保持有效的一方。

    youdao

  • However, unless otherwise agreed by both Parties, the Engineer shall not delegate the authority to determine any matter in accordance with Sub-Clause 3.5 [Determinations].

    但是工程师不能授予按照第3.5款【决定】的规定决定任何事项权力除非合同双方另有协议

    youdao

  • The Employer shall not terminate the contract under this Sub-Clause in order to execute the Works himself or to arrange for the Works to be executed by another contractor.

    雇主为了自己实施安排另外的承包商实施工程,而根据终止合同

    youdao

  • Any such delegation shall be effected in accordance with sub-clause 2. 4 and for this purpose such independent inspector shall be considered as an assistant of the Engineer.

    这种委托第2.4分项条款办理,这种检验员作为工程师助手。这种任命通知书由工程师至少于14天前发给承包人。

    youdao

  • Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine this cost, which shall be included in the Contract Price.

    接到通知后工程师依据第3 . 5【决定】,对此费用作出商定决定加入合同价格。

    youdao

  • Effect shall be given to the measurement and valuation of variations under sub-clause (c) of this clause in Interim Certificates and by adjustment, if required, of the Contract Sum Project Schedule.

    根据本条(c)款规定,并且需要通过合同总价进度计划》的调整,在《期中付款证书》中使对变更测量估价生效

    youdao

  • The if clause determines whether the value of the ResponseRequested sub-element for a given comment is equal to Yes.

    if判断给定评论ResponseRequested 子元素的是否等于 “Yes”。

    youdao

  • The if clause determines whether the value of the ResponseRequested sub-element for a given comment is equal to Yes.

    if判断给定评论ResponseRequested 子元素的是否等于 “Yes”。

    youdao

$firstVoiceSent
- 来自原声例句
小调查
请问您想要如何调整此模块?

感谢您的反馈,我们会尽快进行适当修改!
进来说说原因吧 确定
小调查
请问您想要如何调整此模块?

感谢您的反馈,我们会尽快进行适当修改!
进来说说原因吧 确定