After roller compaction, the wet density of RCC would be measured by sampling from the digged pit or by nuclear densimeter.
碾压后,挖坑取样或采用核子密度水分计选点测量碾压混凝土的湿密度。
Once roller compaction is completed for each layer, apply rapid test of the density and porosity with a nuclear densimeter…
每层碾压完毕,用核子密度仪快速检测压实密度和孔隙率,…
The massive project practice proved the VC value has the remarkable influence to the roller compaction concrete performance.
大量工程实践证明,VC值对碾压混凝土的性能有着重要影响。
The joint grouting techniques in roller compaction concrete structure is one of the most important works in dam building technology.
在碾压混凝土结构中进行接缝灌浆,是目前坝工研究的重要技术问题。
The output of this research work increases the confidence of using impact roller compaction technique in the field of shallow ground liquefaction treatment.
研究成果证明了冲击碾压法在消除浅层地基液化领域的适用性。
The best roller compacted parameter is determined by roller compaction test. Filling and roller compaction are carried out strictly in accordance with dam filling techniques.
通过碾压试验确定了最优碾压参数。对填筑料、碾压等严格按照坝体填筑施工技术要求施工并严格进行质量检查与控制。
All the targets for roller compaction parameters of filling materials for the main dam and associated DAMS of the upper reservoir were determined through in situ roller compaction tests.
通过现场碾压试验,确定上库主副坝各种填筑材料达到设计指标所需的各项碾压参数指标。
A method to describe the over-consolidated condition resulted from the in-situ roller compaction test is proposed by setting the initial value of loading function in the finite element analysis.
提出了在有限元计算中通过给定加载函数初始值的方法来描述坝料由碾压过程所致的初始超固结状态。
By analysing the monitoring data and adjusting the construction procedure in time, the relative displacement at contact surface of the wall footing caused by non uniform roller compaction of tran...
通过资料分析并及时调整施工程序,控制了因两侧过渡料碾压不均衡产生的墙底接触面错动。
By analysing the monitoring data and adjusting the construction procedure in time, the relative displacement at contact surface of the wall footing caused by non uniform roller compaction of tran...
通过资料分析并及时调整施工程序,控制了因两侧过渡料碾压不均衡产生的墙底接触面错动。