• 第四讲述如何创建项目进度计划

    Chapter 4 describes how to create a project schedule.

    youdao

  • 网络计划技术项目进度计划核心技术。

    Network planning technique is the key technique of network scheduling and planning.

    youdao

  • 目前工程项目进度计划编制多采用网络计划方法

    Project network technique is presently a frequently-used method to make project schedule plan.

    youdao

  • 分配资源确定项任务所需时间制定项目进度计划

    A project schedule is created by assigning resources and determining the calendar time required for each task.

    youdao

  • 本文首先项目进度计划周期项目进度超期原因进行总结分析。

    First, this paper searched the reasons of the project's long duration and delaying.

    youdao

  • 项目进度计划安排项目人员的设置在项目管理非常重要作用

    The arrangement of the Project Schedule and allocation of the project staffing play a very important role in the PM.

    youdao

  • 亟待开发种科学、可行项目进度管理方法保证项目进度计划实现

    So we need to focus on a new and systematic method to guarantee the in-time completion of the projects.

    youdao

  • 工作说明资源列表一旦创建完成项目经理就应该制定项目进度计划通常以下几步。

    Once the statement of work and the resource list have been created, the project manager should build a project schedule. This is usually done in several steps.

    youdao

  • 同时结合企业另一案例资源平衡优化项目进度计划保证项目最终完成并做出评价

    Meanwhile, combined with another example of XX Company, the evaluation of the adjustment has been done with resource balance method to optimize the accomplishment of projects.

    youdao

  • 本文阐述了项目进度计划确定关键目的意义深入分析传统项目计划方法存在问题

    This paper illustrates the goal and significance of identifying critical chain in project scheduling, and analyzes the drawbacks introduced by the conventional project scheduling methods.

    youdao

  • 通常制订项目进度计划一个反复迭代过程过程确定每个活动每个里程碑开工日期完成日期。

    Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones.

    youdao

  • 讨论项目进度计划冲突资源相关关键任务、关键任务以及关键任务提出统一定量表示方法

    This paper discussed the critical task, critical task set and critical task group involved conflict resource in a project scheduling scheme, and put forward a unified quantitative express method.

    youdao

  • 应该包括估算项目进度计划以及评审会议上做出任何修改。第三包括一个用于产生WBS和估算的课重复过程

    It should also include estimates and a project schedule, including any revisions that were made during the review meetings. Chapter 3 contains a repeatable process for generating a WBS and estimates.

    youdao

  • 检查任务1.1时,马上意识虽然项目进度计划没有用图示标明,但是这个任务同一个更的任务2.1之间存在依赖关系。

    Having examined task 1.1, you would immediately realize that although this is not graphically marked in your project schedule, there is a dependency between this task and an earlier task 2.1.

    youdao

  • 并且列举了计划实际成果。本文着重论述电网建设项目进度计划编制依据、方法内容以及在实际管理需要特别注意的问题

    It stresses the foundations, measures, contents of power grid project processing plan, while drawing construction plans, as well as the tips and major problems in management practice.

    youdao

  • 模式项目进度计划系统整体出发着重强调并行项目之间相互协调编制步骤分为项目结构分解项目活动时间估算计划编制。

    The schedule in this pattern emphasized the harmonization of parallel projects based on the whole system, and its developing steps include structure analysis, estimation of time and planning.

    youdao

  • 计划评估跟踪门户项目进度并非一个概念

    Planning, estimating, and tracking the progress of your portal project is not a new concept.

    youdao

  • 评估一个计划模型文档一些其他不可执行的表现物美好出色之处时,你只是在推测项目质量进度

    As long as you are assessing the beauty or goodness of a plan, model, document, or some other nonexecutable representation, you are only speculating about quality and progress.

    youdao

  • 管理这个项目计划中,项目经理必须这个项目技术领导者一起合作评估工作完成进度

    In managing the project plan, the project manager must work with the technical leads of the project to assign work, and to assess work completion.

    youdao

  • 项目经理建立第一个迭代项目计划安排方法集成项目资源定期所有涉众报告进度

    The project manager creates a first iteration project plan and arranges the resources for the methodology integration project, reporting on progress regularly to all stakeholders.

    youdao

  • 项目经理需要针对计划监测正在进行工作进度预测所期待最终成本

    The project manager then needs to establish what has actually happened as opposed to what was planned and to forecast the expected final costs.

    youdao

  • 制订计划非常关键的,不仅跟踪进度是如此而且首先确保能够按时完成项目也是如此

    Planning is key, not only for tracking your progress, but to insure that you can finish on time in the first place.

    youdao

  • 测试激发因素和测试努力相关文档例如项目进度、一个需求文档或者一个项目计划

    Test motivators are documents that may relate to the test effort, such as a project schedule, a requirements document, or a project plan.

    youdao

  • 计划 ——定义项目战略包括开发交付项目计划计算规模各个部分的规模、定义工作进度主要检查点建立里程碑

    Planning - Define a strategy to develop and deliver a project plan, calculate overall and detailed sizing, define a work schedule, and establish milestones for major checkpoints.

    youdao

  • 欧盟驻外机构根据这计划援助项目实施发挥大的作用同时欧盟内部将建立一个更加精干组织加快援助进度

    EU missions abroad will get a bigger role in implementing programmes on the ground, while a better staffed organisation will be set up within the Commission to speed up aid delivery.

    youdao

  • 可以调查趋势学习如何计划的时规划实际比较应该能够改进您的项目计划时间进度安排。

    You can examine trends, and should be able to improve your project planning and scheduling as you learn how your projected timeframes compare to actuals.

    youdao

  • 项目技术团队结构时间计划非常有益于阻碍进度的情况下合并RUP其他工具

    The project's technologies, team structure, and schedule were very conducive to incorporating the RUP and other tools without impeding progress.

    youdao

  • 在不使用全面项目计划软件时,技术人员如何帮助跟踪项目进度

    How can technical practitioners assist in tracking the progress of the project without using a full-fledged project plan or software?

    youdao

  • 一方面,项目管理者更加关注资源进度成本等方面管理项目计划

    The project manager, on the other hand, is more concerned with managing the project plan in terms of resources, schedule, and cost.

    youdao

  • 一方面,项目管理者更加关注资源进度成本等方面管理项目计划

    The project manager, on the other hand, is more concerned with managing the project plan in terms of resources, schedule, and cost.

    youdao

$firstVoiceSent
- 来自原声例句
小调查
请问您想要如何调整此模块?

感谢您的反馈,我们会尽快进行适当修改!
进来说说原因吧 确定
小调查
请问您想要如何调整此模块?

感谢您的反馈,我们会尽快进行适当修改!
进来说说原因吧 确定