水电工程施工总布置时间、空间逻辑关系复杂,具有动态交互的特性。
Construction site layout of Hydropower engineering has the complicated logic relation of time and space, coming with the characteristic of dynamic interaction.
但就现阶段的研究成果看来,有关施工总布置动态可视化系统的研究并不完善。
However, judging from the current situation, results of the visualization for construction site layout are not perfect, and the complicacy of the construction site layout leads to it.
并将其运用于其宗水电站施工总布置分析中,验证本文研究思路的合理性和有效性。
SVS is successfully applied to the analysis for the construction site layout for Qizong hydropower station, which validates the rationality and validity of the thought in this thesis.
龙滩水电站工程通过利用工程弃渣和统一调配使用场地,实现了狭窄坝区的施工总布置。
It realized rational general layout in narrow area by making use of abandoned excavated materials and overall construction site allocation in Longtan Hydropower Station.
本文结合GIS在水利水电工程施工总布置可视化研究中的实际应用情况,建立了基于GIS的施工总布置可视化信息系统。
Considering existing circumstance of GIS application in Hydroelectric engineering construction layout, GIS-based construction layout visualization information system is built.
本文结合GIS在水利水电工程施工总布置可视化研究中的实际应用情况,建立了基于GIS的施工总布置可视化信息系统。
Considering existing circumstance of GIS application in Hydroelectric engineering construction layout, GIS-based construction layout visualization information system is built.
应用推荐