本文结合工程实践,通过现场试验分析研究提出锚杆桩抗拔极限荷载直接或间接的确定方法,并提出了合理的施工方案。
The direct or indirect method to determine ultimate uplift load of anchored rod pile is proposed herein based on field tests in association with engineering practice.
如何利用现场抗拔静载试验中未达到破坏的工程试桩数据来确定其抗拔极限承载力是一个重要的工程问题。
It is very important for engineer to determine the uplift ultimate bearing capacity by using the data of non-destructive test of pile.
以新疆地区某高压输电线冻土桩基础受力分析为背景,在人工冻结条件下,进行了单桩的室内抗拔模型试验。
Aimed at the pile foundation in frozen soil of a high voltage transmission line project in Xinjiang Region, a laboratory tensile model test is carried out under artificial frozen condition.
为了了解扩底抗拔桩的抗拔机理和抗浮特点,进行扩底抗拔桩和等截面抗拔桩的试桩试验。
In order to understand float resisting mechanism and its characteristic a test on the bored cast-in-place pile with enlarged bottom and up-lift resistance pile with equal section is carried out.
通过使用ANSYS软件,对桩-桶基础上拔试验进行有限元数值模拟。
Numerical simulation of finite element method for pile-bucket foundation under uplifting load were conducted by making use of ANSYS software.
利用直桩,斜桩的抗拔、抗压静载荷试验对微型桩的承载力进行了探讨。
Based on the uplift tests and the loading tests of vertical and raking piles the bearing capacity of mini piles is discussed.
在现场试验基础上,研究沉管干振挤密抗拔防浮碎石桩在拉压循环荷载和拉拔循环荷载下单桩及其抗拔钢筋的性状。
Based on the in-situ tests, the behaviors of single diving dry-vibrated compacted and anti-pull stone column with steel bars are studied during the compression-uplift cyclic loading.
试验结果表明采用二次注浆工艺能显著提高微型桩抗拔极限承载力,有效地减小抗拔桩位移;
The test results indicate that the compaction of soil from twice pressure groutings can raise the ultimate uplift capacity of micropiles obviously and reduce the displacement effectively.
数值模拟了上拔荷载、桩上拔位移与时步的关系,并与宏观物理实物试验的实测结果作了对比分析;
The relations between uplifting load , displacement and time were simulated numerically and compared with the results of actual pile tests, and the ultimate uplifting bearing capacity was defined.
数值模拟了上拔荷载、桩上拔位移与时步的关系,并与宏观物理实物试验的实测结果作了对比分析;
The relations between uplifting load , displacement and time were simulated numerically and compared with the results of actual pile tests, and the ultimate uplifting bearing capacity was defined.