• 估计完成每一项任务需要平均时间

    The average working time required to complete each task is estimated.

    youdao

  • 还要了解何时估计不足以及某些任务项目计划好的很短时间没有完成

    It is also about knowing when estimates are way too low and that something will not be finished in the ridiculously short time your project has scheduled.

    youdao

  • 开发工作估计条需求所需要工作量以及开发团队时间(一次迭代)里能完成的工作量。

    Development estimates how much effort each story will take, and how much effort the team can produce in a given time interval (the iteration).

    youdao

  • 例如假设完成一个任务花费估计时间3个月

    For example, suppose an estimated value of the time it will take to do a task is 3 months.

    youdao

  • 因此比如估计5完成任务,如果考虑日常会议电子邮件电话呼叫复查后,实际上需要89天的时间才能完成

    So, for example, a task estimated at five days may actually take eight to nine days to complete once the daily meetings, e-mails, phone calls, and reviews are taken into account.

    youdao

  • 了解软件组件安装顺序配置非常重要,因为这样就可以准确估计完成各个任务所需时间

    Knowing the installation order and configuration of the software components is important, as is being able to accurately estimate the time required to complete various tasks.

    youdao

  • 第三完成工作项目过于乐观尽管多年来的经历总是少估计实际需要时间

    A third is undue optimism about how quickly I can complete work projects, despite many years of experience in underestimating the time actually required.

    youdao

  • 测试项目早期阶段可以提供高层次完成测试计划活动所需时间估计以及运行所有测试所需的时间精力估计

    In the early stages of a test project, you can provide high-level estimates of the time required to complete your test planning activities, and the time or effort required to run all of your tests.

    youdao

  • 考虑如下事例:如图1上半部分所我们任务A任务b,我们估计完成它们各需要时间我们的时间上它们总共占用了16天的时间

    Consider this example: we have Tasks a and b, both of which we've estimated at eight days each, taking a total of 16 days in our schedule, as shown in the upper portion of Figure 1.

    youdao

  • 估计每天编写数据库访问完成单元测试因此,150 个要用 150时间

    You estimate a day to write each database access class and unit test it, so 150 tables at one table per day is 150 days.

    youdao

  • 我们一个清晰技术方案更加可靠估计我们觉得能够完成时间计划。

    We had a clean technical solution, more reliable estimates, and a schedule that (although tight) we felt would get us to the end.

    youdao

  • 我们应该客观实际的估计任务到底需要多长时间完成如果他们计划的时间长,我们就从最低优先级的任务开始取消任务。

    We are always realistic with ourselves about how long tasks take, and if they take longer than normal, we start cutting tasks that are lowest priority.

    youdao

  • 这次失败首先源于没有正确地估计作业量,其次是没安排一个最佳时间完成作业。

    The failure started by not properly estimating the size of the task, and continued when she didn’t use her calendar to determine the best time to start the assignment.

    youdao

  • 赖安公司的这些精打细算的计划没有付诸实际;官方估计改造所有飞机卫生间至少需要2时间才能完成

    Ryanair's pay-per-potty scheme hasn't yet materialized; officials estimate it will be at least two years before they have removed and reconfigured the airplane bathrooms.

    youdao

  • 保守估计Google时间完成了1000万本书数字化

    So a conservative estimate has Google digitising at least 10m books a year.

    youdao

  • 如果估计99%时间花费任务,那么你是大大低估完成任务所需要时间

    99% of the time if you guess at this you will greatly underestimate the time a task takes to be completed.

    youdao

  • 一步中要求团队分析估计完成每个活动需要时间

    This step requires you and your team to analyse how long it will take to accomplish each of the activities. These estimates can be quantified through the following tools.

    youdao

  • 完成所有估计的工作之后,您可以看到每一个事例总体估计值,以及整个Sprint阶段的时间估计值。

    When you have entered all estimates, you can see the total estimates for each story, as well as for the whole sprint.

    youdao

  • 我们估计完成这项工作需要一周时间

    We estimate that it would take a week to finish the job.

    youdao

  • 还有一些由于注意力容易分散以至于忘了时间还有从来也不会正确估计时间留出时间按时完成工作。

    There are also those who are so easily distracted that they simply "lose track" of time, while others never learn to estimate or leave the time they need to keep on schedule.

    youdao

  • 从根本上人类真的善于估计完成工作所需时间资金即便他们以前做过这项工作。

    Fundamentally speaking, humans really not very good at estimating time or funds required to complete the work, even if they have done this work before.

    youdao

  • 对策:把每天老师布置作业大概时候估计孩子需要完成任务(包括家长布置任务)进行一个时间预计

    Countermeasures: to do a rough time estimate the daily homework assigned by the teacher, children will need to complete the task (including parents set tasks) for a time expected.

    youdao

  • 估计完成填写申请表时间15分钟以内

    Estimated time needed for completing the application is 15 minutes or less.

    youdao

  • 采用C语言完成灰度转换、图像差分、中值滤波、光流估计、形心确定、高速球控制等软件模块程序设计,调试出程序执行时间并做了实时性分析;

    Most software module programs are compiled with the language C, and the execution time of the program is debugged and the real-time performance compared as well.

    youdao

  • 每个视图提供一个区域,该图指定持续时间估计工作量,绘制完成工作进度

    Each view provides an area graph that charts the progress of completed work against the total estimated work for the specified time duration.

    youdao

  • 每个视图提供一个区域,该图指定持续时间估计工作量,绘制完成工作进度

    Each view provides an area graph that charts the progress of completed work against the total estimated work for the specified time duration.

    youdao

$firstVoiceSent
- 来自原声例句
小调查
请问您想要如何调整此模块?

感谢您的反馈,我们会尽快进行适当修改!
进来说说原因吧 确定
小调查
请问您想要如何调整此模块?

感谢您的反馈,我们会尽快进行适当修改!
进来说说原因吧 确定