the monthly report to the client shows zero schedule variancehowevermembers of the team know that amilestone has been missed that will cause an overall delay to the projectwhich one of the following is being inadequately reportedacommunication plan variance bresource management plan ccritical path status drisk analysis
给客户的月度报告显示进度变化为零,然而团队成员知道错过了一个里程碑,这将导致项目的全面延迟,以下其中之一是报告不充分,沟通计划差异,资源管理计划,关键路径状态,风险分析