Under the complex geological condition where the backfill is on thick soft clay, the design method of combining fly ash concrete pile and lime pile is presented.
针对深厚软粘土上覆新回填土的复杂地质条件,提出了粉煤灰混凝土桩与石灰桩联合进行地基处理的设计方法。
The foundation treatment of compaction pile method is applied in many power plant projects, especially lime-soil compaction-expansion pile method.
挤密桩法地基处理在电力工程中广泛应用,特别是灰土挤密夯扩桩法。
Based upon the working principle of lime-rock pile, design and construction method of lime-rock pile reinforcing soft soil foundation, corresponding treatment measures to common problems are proposed.
介绍了灰石桩的成桩机理,阐述了灰石桩加固地基的设计及其施工方法,并对灰石桩加固软弱地基过程中常见的问题提出了相应的处理措施。