• 参与所有施工改造项目

    Participates in all construction and modification projects.

    youdao

  • 无论在室内还是室外,真实一直所有施工选择核心

    Both indoors and outdoors, honesty has been at the core of all construction choices.

    youdao

  • 负责公司所有施工地坪的终身成本维修长期进行跟踪服务

    We will undertake all the maintain for our contracted projects and follow up service.

    youdao

  • 所有施工必须卖家专人监督下进行,施工提交施工计划(可能需要交纳施工保证金)。

    All work must be supervised by Seller's personnel and a work plan must be submitted for approval prior to the work starts (a deposit may be required if applicable).

    youdao

  • 确保所有施工区域必须足够照明(舱内防爆照明),以便于施工检查尤其是船坞平船底

    To ensure allworking area has enough illumination (it was anti-explosion illumination insideof tank) to easy for working and inspecting, especially flat bottom in drydock.

    youdao

  • 我们公司涉及所有施工活动,包括:打桩土建工程机械安装配管电气仪表油漆保温绝缘工作

    Our company cover all construction activities, that is: piling, civil engineering, mechanical erection, piping, electrical, instrumentation, painting and insulation work.

    youdao

  • 我们公司涉及所有施工活动,包括:打桩土建工程机械安装管、电气、仪表、油泼裢保温绝缘工作

    Our company cover all construction activities that is: piling civil engineering mechanical erection piping electrical instrumentation painting and insulation work.

    youdao

  • 项目有一个项目经理我们客户一起协调所有施工安装,确保工程环节同步推进最后按时完工。

    A Heliono project manager coordinates all engineering and installation activities with our customers to properly phase all aspects of the project and meet critical schedule dates.

    youdao

  • 甚至所有这些还不能按时得到东西:国会大厦东面一个预计丑陋施工现场

    And even all that cash failed to get the thing built on time: the east front of the Capitol was an ugly construction site for four years longer than scheduled.

    youdao

  • 所有房屋单元现场预制施工每个单元利用下层邻居楼顶做为自己屋顶花园空间

    All of the units were prefabricated on-site, and each has its own rooftop garden space located on the roof of the neighbor below.

    youdao

  • 不仅如此到了2016年,世界涡轮机制造能力也不能满足同时施工所有项目

    Not only that, but by 2016 there's not enough turbine manufacturing capacity in the world to be able to deliver the turbines to all the projects that need them at that time.

    youdao

  • 所有发电量超过一亿二千五百万发电厂石油发电厂于2007年前进行类似施工

    Similar works will be carried out on all oil-fired and coal-fired power plants with a capacity over 125 megawatts by 2007.

    youdao

  • 所以我们现在努力确保社会性别的意义纳入我们的一切工作土地所有设计社会保障制度,到基础设程建设

    So we'll now work to ensure that the implications for gender are embedded in everything we do, from land-titling, to designing social security systems, to infrastructure projects.

    youdao

  • 特别强调这个联系创造材料对话显示施工过程的所有阶段

    This contact, expressly highlighted, creates a dialog of materials showing all the phases of the construction process.

    youdao

  • 所有施工过程中被砍伐树木用来作为建筑家具材料

    All trees felled during the construction were used to provide wood for the building's furniture.

    youdao

  • 差不多所有工程项目中施工一个复杂过程

    Construction is a complicated process on almost all engineering projects.

    youdao

  • 综合工区:负责所有机械设备维修保养以及本项目的辅助工程施工管理工作

    Complex processing area: be responsible for repair and maintenance of all mechanical equipment, construction of the project's ancillary works and other management work.

    youdao

  • 赛科施工现场所有人员随身携带洁净的、质量安全眼睛

    All personnel on the SECCO Construction Site are required to carry on their person a pair of clean, good quality Safety Spectacles.

    youdao

  • 投标工程清单项符合材料设备清单。分包商确认所有材料及其施工方法满足投标技术规范的要求

    Material and Equipment list as Tender BOQ listed. Sub contract confirmed that all materials and it installation method are meeting the requirement as specified in the tender specifications.

    youdao

  • 所有施工剩余材料废料均已按要求合适地方

    All the residual materials and waste materials are moved to the proper place.

    youdao

  • 我们希望所有施工机械投保

    Wee also hope to have all of our construction machinery insured as well.

    youdao

  • 竣工验收之前根据规定提交资料份数提前整理好桩基施工的成套资料,所有必须签署姓名的地方不得遗漏。

    Prior to completion and acceptance of works, sets of data on pile foundation construction shall be prepared early and signatures of name can not be lost according to the copies of documents submitted.

    youdao

  • 所有人员必须保证配备足够的个人保护设施,能够根据他们所进行施工作业正确使用设备仪器。

    All personnel shall ensure that they are wearing adequate protective safety clothing and using the correct safety equipment and devices fit for purpose in respect to the activity they are undertaking.

    youdao

  • 其中人工建造构筑物设计施工缺陷造成损害的,所有治理设计、施工承担连带责任

    Build artificially among them because blemish of design, construction is caused, build thing damage, assume joint liability by the everybody, person that supervise person and design, construction.

    youdao

  • 系统安装施工符合相应IEC国际标准中国国家标准规范所有动力电缆控制电缆信号电缆布线分开

    The system shall be installed and constructed in compliance with relevant IEC or China national standards or specifications. Power, control, and signal cables shall be wired separately.

    youdao

  • 如今升降机已经成为国内外所有建筑施工工程场所垂直运输不可缺少的重要先进技术设备

    Nowadays, the lift has become the home of all construction sites for vertical transportation indispensable important advanced technology equipment.

    youdao

  • 所有结构施工钢筋使用规格参照结构工程师施工图纸

    Refer to Structural Engineer's Drawings for all Structural Works and Steel Reinforcing Specifications.

    youdao

  • 所有结构施工钢筋使用规格参照结构工程师施工图纸

    Refer to Structural Engineer's Drawings for all Structural Works and Steel Reinforcing Specifications.

    youdao

$firstVoiceSent
- 来自原声例句
小调查
请问您想要如何调整此模块?

感谢您的反馈,我们会尽快进行适当修改!
进来说说原因吧 确定
小调查
请问您想要如何调整此模块?

感谢您的反馈,我们会尽快进行适当修改!
进来说说原因吧 确定